Welcome to The World Of
 
   TMM International Home : Mypage
TMM India Home : Mypage  

:: Back 2 School
Finance
Human Resources
Information Technology
Manufacturing
Marketing
Strategic Management
 


Apply Theory Of Constraints (TOC) and provide time buffers for any unforeseen delays in projects

Apply TOC to eliminate safety time

Conventional project management technique provides safety time for individual activities in a project. The conventional approach focuses on successful on-time completion of each individual activity in a project. However, the Theory of Constraints (TOC) approach focuses on successful on-time completion of the entire project. According to TOC, the main constraint in any project is the time taken for completion of the critical chain. Therefore emphasis is laid on completing activities in the critical chain without wasting any time. Hence, cutting safety time from individual activities eliminates the major cause of time wastage, thereby removing the constraint.

However, this does not mean that the project is to be left unprotected against any unforeseen delays in any individual activity. The project is to be guarded against delays by providing time buffers. Four different kinds of time buffers provided to guard the project are:

  • Project buffers
  • Feeding buffers
  • Resource buffers
  • Constraint buffers.

These buffers provide the necessary cushioning to individual activities to enable them to accomplish the final goal of completing the critical chain in the least possible time.

Critical chain in a project is defined as the longest sequence of activities from several different paths, connected by activities performed by common resources. The safety time provided for the critical chain is defined as the project buffer. The safety time is removed from individual activities and is utilised to create the project buffer. Critical chain activities, which take less than the median time for completion, partially compensate for activities, which take longer than median time. The project buffer absorbs any further delays.

PERT,PROJECT BUFFER & FEEDING BUFFER

In the PERT (Programme Evaluation and Review Technique) chart shown in figure 1 the alphabets inside the circles represent the activities and the numerals on top of the circles represent the estimated time of each activity. The activities connected by arrows shown in bold indicate the critical chain.

It is clear from the chart that the minimum time required to complete the project is 56 days. Even a very conservative estimate will indicate that the safety time for each activity is about half of its estimated time. If the safety time from each activity is removed, the project duration is reduced to 28 days. As a thumb rule, it is suggested to add about half of the removed safety time to the critical chain as project buffer. In the example, 14 days are added to the critical chain as project buffer. The revised project completion time is 42 days, which is 14 days less than the original estimate.

Feeding buffer is the extra time provided for activities on the non-critical path, which merge with the critical chain. The feeding buffer provides a guard against delays in non-critical paths affecting the critical chain. The feeding buffer, as a thumb rule is normally assumed half of the time removed from activities on the feeding path. The feeding path CF merging into activity I in the PERT chart in figure 1, sets free 8 days of safety time. Therefore, the feeding buffer is taken as 4 days. Activity F should be scheduled to be finished 4 days before activity I is to begin. The feeding buffer does not increase the project completion time. If at all the feeding buffer is inadequate, resulting in delays in critical chain activities, the project buffer absorbs it.

RESOURCE BUFFER & CONSTRAINT BUFFER

The Resource buffer guarantees the availability of resources required for activities on the critical chain. Providing scheduled idle time for the resource establishes the resource buffer. Another way is to send timely updates to the resource manager of the project progress, so that the resource is available to perform the critical chain activity as scheduled. Critical chain activity can therefore begin even before its scheduled time, if required. This early start can either shorten the project completion time or compensate for any delays in the critical path.

A constraint buffer is established to maintain the schedule of a constraint resource handling multiple projects. It ensures that all the required project activities are completed, before the constraint resource begins a scheduled specific activity. The scheduling becomes complicated when there are several constraint resources handling multiple projects. It is advisable to use specialised software to efficiently resolve the resource sharing problem.

Projects involve a high level of uncertainty and depend heavily on the contributions of individuals. Project manager needs to work with different departments involved in the project to estimate lead times so that they meet the needs of the critical chain. The critical chain concept starts with a set of talented and driven project managers and assumes that the resource constraints are within the scope of the project but not in its leadership. In truth, leadership may be the larger constraint.

Related Reading: Manage your projects for success: An application of the theory of constraints. Umble, M.; Production and Inventory Management Journal, 06/2000.

Figure 1

Introduction  |  Contents   |  Top

Feedback or Comments?

Designed and Maintained by C & K Management Limited

© Copyright 2003 C & K Management Limited